Wilson removed approximately 33 miles of overhead line and installed about 33 miles of overhead and 4 miles of underground line. Wilson successfully coordinated outages with Avista and was able to complete work at "no vehicle access" sites by hand digging pole holes and setting new poles with helicopters.
View the embedded image gallery online at:
https://wilsonconst.com/services/distribution-construction/item/39-avista-utilities-wilbur-12f2-feeder-project-wa#sigProId0272323d98
https://wilsonconst.com/services/distribution-construction/item/39-avista-utilities-wilbur-12f2-feeder-project-wa#sigProId0272323d98
Wilson mobilized for multiple work orders which were part of Avista Utilities Grid Modernization project, improving the reliability of Avista's electrical distribution system.